Permanent way hut, roof repairs

April 14th, Preston under scar

                                     The old roof material was stripped off and the         The new roof applied, hopefully curing any leaks.

                                     concrete was primed.

 

Permanent way hut window replacement

March 31st, Preston under scar

                                    Before                                                                                After

 

 

Crossing gate replacement

March 24th, Scruton crossing

 

 

 

 

Tree removal and crossing maintenance

March 24th, Smiths UWC near Constable Burton

 

 

Further west of the crossing, tree removal is taking place. (left)

A little later on.

 

 

Drainage and UWC maintenance

March 17th, Wilkinson UWC west of Leyburn

There definitely is track there, trust me!

 

This is how it looks now.

 

Drains were dug out.

 

The drain was also cleared on the west side of the crossing.

 

 

Tree removal

March 10th, East of Newton Grange crossing

 

A good opportunity to try out the new chipper

 

The chipped wood makes an excellent mulch, hopefully suppressing any regrowth.

 

looking West before the trees were removed

 

After

 

Crossing maintenance

March 7th, Aiskew road crossing

 

After years of heavy traffic pounding over the crossing, the rubber blocks are removed to maintain a level and smooth road surface. (apologies for some blurry images)

Removing the rubber blocks

 

Once the blocks are out, the area underneath was cleaned.

 

Any broken clips were replaced with new ones.

 

A concrete mix was used to build up a level base.

 

With the correct depth and a level base the rubber blocks were replaced.

 

The crossing blocks replaced and level.

Sleeper replacement

March 3rd, East of Constable Burton near Akebar

 

Sleepers replaced.

 

Just the cleaning left to do

 

Tree removal and UWC crossing extension

March 3rd, East of Leyburn station

 

Before

 

After, most trees were removed on the right side of the photo

 

The crossing has been extended to allow larger vehicles to access the users property. The new timber sits on the left next to the existing in the four foot.

Press the 'Home' button on your keyboard to return to the top of the page