Ballasting

Friday 13th June, West of Wensley

 

Loading the ballast at Redmire, Mike makes a start

 

Mike was too slow so we got the machine on the job

 

The train is loaded and ready to go

 

The train was moved up near Wensley, the ballast was then dropped as the train crept forward

 

That will keep the rabbits off!

 

 

Sleeper replacement

Saturday 7th June, West of Leyburn

Spot resleepering taking place just west of Leyburn station

 

 

 

 

Sleeper replacement

Friday 23rd May, Bedale Station

 

The Friday night team start work on digging out the old sleepers

 

Work moves swiftly, the Friday night team is mix of Ops and Infrastructure members working together.

15 Sleepers later and the Friday night team became the Saturday morning team!

 

 

 

 

Level crossing deck replacement

Saturday 17th May, Finghall Crossing

 

The time had come for new timbers to be laid at Finghall

 

The old timbers were removed, some proved more difficult than others

 

The trackbed was cleared of mud and a layer of new ballast put down

 

The new timbers are down and the road is reopened

 

 

 

 

Drainage cleaning

Friday 2nd May,Bridge 29 between Leyburn and Wensley

Works train taken up so JCB can dig out new drainage ditch

 

Old drains required unblocking

 

All this brought to you by Leeming Bar Traction Maintenance Depot, here can be seen the trains high quality headboard just before the sun set.