Sleeper replacement

Saturday 30th August, Redmire

 

A sleeper in need of replacement

 

The old sleeper is removed and the bed is prepared, ready for the new one.

 

The new sleeper in and packed. 10 sleepers were changed today.

 

Sleeper replacement

Saturday 16th August, Redmire

Old sleeper, ready to be replaced

 

Drilling

 

sleepers.....

 

Tools were left to one side as the Steam loco runs round

 

The end of the line..............for now!

 

 

Sleeper replacement

Saturday 2nd August, Harmby

Digging out the old sleepers

 

Drilling, ready for the chair screws to be inserted

 

Using the Impact wrench to tighten up the chair screws

 

A total of 16 sleepers were changed

 

 

 

Sleeper replacement

Friday 18th July through till Saturday 19th

The Friday night gang spent a good 12 hrs replacing a total of 31 sleepers, in order to increase line speed on a particular section of track.

Work started at 18:00hrs, at 18:03 Adrian is seen here full of enthusiasm

 

In the early hours, the pace had started to slow but an end was in sight.

 

One of the last sleepers

 

With sleeper no. 31 in and packed, the temporary speed restriction could removed from that section

 

All done and heading back towards Leeming at 8:00 on Saturday morning