July - August
![]()
![]()
![]()
Sleeper replacement
Saturday 16th August, Redmire
Old sleeper, ready to be replaced
Drilling
sleepers.....
Tools were left to one side as the Steam loco runs round
The end of the line..............for now!
![]()
Sleeper replacement
Saturday 2nd August, Harmby
Digging out the old sleepers
Drilling, ready for the chair screws to be inserted
Using the Impact wrench to tighten up the chair screws
A total of 16 sleepers were changed
![]()
Sleeper replacement
Friday 18th July through till Saturday 19th
The Friday night gang spent a good 12 hrs replacing a total of 31 sleepers, in order to increase line speed on a particular section of track.
Work started at 18:00hrs, at 18:03 Adrian is seen here full of enthusiasm
In the early hours, the pace had started to slow but an end was in sight.
One of the last sleepers
With sleeper no. 31 in and packed, the temporary speed restriction could removed from that section

All done and heading back towards Leeming at 8:00 on Saturday morning