July - August
![]()
![]()
![]()
Tree removal
August 25th, Aiskew Crossing
Before, looking towards the road crossing, facing Leeming Bar.
Trees were removed to improve visibility of the crossing and the warning lights.
![]()
Drainage and sign erection
July 21st, Redmire railhead
Recent problems with drainage required a new pipe to be laid under the trackbed
The excess water is now linked directly to the drainage system
New signs for footpath crossings
![]()
Road crossing upgrade
July 14th, Aiskew crossing
The old crossing with the rubber units
Using the bruff to remove the old rubber units
All the rubber units and metal retainers were removed. A section of the old road surface was also removed before being filled in with tarmac right up to the rail. The finished surface is a lot smoother and gives better grip in wet weather.
![]()
Road crossing replacement
July 1st, Yafforth crossing
The old crossing with concrete sections
The concrete was beginning to show signs of age
The concrete sections were removed
The ballast was leveled and the sleepers cleaned. Any broken clips were also replaced
Before the replacement rubber units are placed in, smaller rubber covers are used to cover the track clips
The finished crossing