Sleeper replacement

21st Sept, Near Aiskew

An expired sleeper is removed and the track bed leveled

 

New sleeper in position and ready for drilling

 

New sleepers in and fishplates oiled, 24 sleepers were replaced

 

 

Crossing replacement

19th Sept, UWC near Aiskew

The old timbers were removed

 

The crossing area is cleaned out and track components are checked before being covered again.

 

A chainsaw was used to cut out the spaces, required for fitting the timber around the chairs.

 

 

 

The crossing finished.